Latest information was posted September 20, 2023
2022 CSO Annual Report - posted September 20, 2023
2023-08-01 CSO 2022 Annual Report Review Letter - posted September 20, 2023
2023-01-13 Removal of Requirement to Submit Significant Rainfall Event Notifications - posted January 20, 2023
2022-06-07 CSO 2021 Annual Report Response - posted July 7, 2022
2021 CSO Annual Report - posted July 7, 2022
2021 CSO Annual Report Review Letter - posted July 7, 2022
2021-07-23 Confirmation of Clause 8 Interpretation - posted August 16, 2021
2021-07-08 Combined Sewer Overflow Analysis Acknowledgement Letter - August 17, 2021
2020 CSO Annual Report Review Letter - posted August 20, 2021
2020 CSO Annual Report - posted August 20, 2021
2019 CSO Annual Report Review Letter - posted January 14, 2021
2019 CSO Annual Report - posted January 14, 2021
Environment Act Licence 3042 - posted November 22, 2019
November 13, 2019 CSO Master Plan Approval Letter - posted November 22, 2019
CSO Master Plan: - posted November 22, 2019
- Cover Letter
- TOC
- Abstract
- Technical Report
- Basis of Estimate Technical Memorandum
- Workbook Description
- Scenario Figures
- CSO Master Plan Summary
- District Engineering Plans
- Alexander District Plan
- District Interconnection Overview Map
- Cost Summary
- Risk Opportunity Matrix
- Standard Details
- Example Screen Sizing Calculation
- Figures
- Latent Storage Options
November 24, 2017 Combined Sewer Overflow Approval - posted on November 28, 2017
Letter of Clarification - July 17, 2017 - posted on July 21, 2017
Clause 8 Clarification Letter - June 23, 2017 - posted July 31, 2017
Advertisement - posted February 9, 2016
Acknowledgement letter - posted February 9, 2016
Environment Act Proposal - posted February 9, 2016
Environmental Approvals Contact: Asit Dey